Terrific progress being made on the uplands new-build.
33 slab penetrations in and signed off by building control, backfilled and now blinding concrete completed ready for the warranty backed DPM to go down.
Superb work by the guys, next up DPMs and RC
Another site coming to an end this week.
4 new plots in the centre of bath completed for @izeo_construction.
Project all completed on time and in budget, looking forward to see this one when completed.
All works completed up to DPC including, piling
Things coming together at the Beaufort West project in Bath.
Steel in as per the engineers design and bending schedule, all signed off with building control and concreted along with up-stands as required.
Next up external retaining wall and toe to engin