The Uplands new build project progressing nicely.
All warranty backed DPMs are in and completed.
All steel reinforcement including the “L” mesh bent A252 in place and tied. All signed off by building control.
Reinforced concrete pad poured and compl
Another site coming to an end this week.
4 new plots in the centre of bath completed for @izeo_construction.
Project all completed on time and in budget, looking forward to see this one when completed.
All works completed up to DPC including, piling
Things coming together at the Beaufort West project in Bath.
Steel in as per the engineers design and bending schedule, all signed off with building control and concreted along with up-stands as required.
Next up external retaining wall and toe to engin