Another RC Raft slab completed recently for @flyingpiginbath.
Excavation, reinforcement, shuttering and concrete completed.
Shuttering being stripped tomorrow and storm drainage connections made.
Thankyou for the business and looking forward to the
Another site coming to an end this week.
4 new plots in the centre of bath completed for @izeo_construction.
Project all completed on time and in budget, looking forward to see this one when completed.
All works completed up to DPC including, piling
Things coming together at the Beaufort West project in Bath.
Steel in as per the engineers design and bending schedule, all signed off with building control and concreted along with up-stands as required.
Next up external retaining wall and toe to engin